Water Treatment Plant, Dösebacka, Kungälv, Sweden
Dewatered Sludge Silo 60 m3 with discharge equipment.
Saxwerk delivered in 2017 one new dewatered sludge silo for the water treatment plant, Dösebacka in Kungälv Sweden.
Saxwerk has delivered, installed and commissioning one sludge silo consisting of a steel silo, sliding frame, discharge screw type DA and electrical cabinet. The system unload sludge to a lorry outside the silo.
Technical data: | |
---|---|
Material: | Dewatered sludge |
Capacity: | 80 m3/h |
Diameter: | 3 500 mm |
Casing Height: | 6 300 mm |
Support Height: | 4 500 mm |
Volume: | 60 m3 |